IFSW: Near Term Evolution of Multimedia Facilities and Equipment

STATUS | Completed
STATUS DATE | 21/08/2009
ACTIVITY CODE |

Objectives

The project objective is to develop an IF Switch Matrix for use in Multimedia Satellite The development is targeted Ka & Ku-Band Multimedia applications, where connectivity and capacity switching is taking place at an IF in the range from 700 MHz and up to 2,5 GHz. The demonstrator will verify the low cost approach for switch elements and a developed switch matrix unit will verify a specific connectivity for a targeted program.

The goal is to integrate the switch-matrices with our existing products, extending the integration and packaging philosophies that have been successfully applied on a number of programs.

Challenges

The key issues in the development is to design and demonstrate an 8 x 16 IF Switch matrix based on multilayer PCB technology. Focus will be on low cost in combination with a highly integration and combination with the existing product range of downconverters, demux (including SAW subchannelization filters) and upconverters. It will be a key issue to extend the integration and packaging philosophies that have been successfully applied on a number of programs.The developed unit will be designed with a modular approach so that several switch matrices can be stacked in different configurations to provide the needed switching capability.

Plan

There are three main milestones in the project; BDR (Baseline Design Review), MTR (Mid Term Review) and FR (Final Review). Program duration is 18 months.

System Studies & Trade Off Analysis

The first phase leading up to BDR consist of the following tasks at T0+4:

  • System optimisation and Building Block Specification
  • Technology Evaluation T
  • est Definition

Equipment Design and Development / Test Development

The second phase ends at MTR (T0+9) and includes:

  • Equipment overall design
  • Switch matrix design
  • Qualification of parts, materials and processes
  • Procurement
  • Test Development

EQM Assembly Integration and Test

The last phase ends at FR (T0+18) and includes:

  • Switch matrix assembly and verification
  • Equipment EQM Assembly and integration
  • Qualification of parts, materials and processes
  • Equipment Test and reports

Current Status

The program is now close to the MTR. Baseline has been chosen and the detailed design is almost finalized. The most challenging issue have been the layout of the multilayer PCB. Through prototyping design rules and technology choices have been verified and implemented in the design. Qualification programs are currently running, and the preliminary results are promising. After MTR the manufacturing, integration and test will take place.