Objectives

R3 IoT offers accessible, dependable connectivity anywhere, giving businesses the information that they need to make informed decisions. 

This project will develop the next generation R3 IoT system, incorporating cutting edge technologies, designing for mass-manufacture, and improving the performance of all elements to ensure the R3 end-to-end Industrial IoT service will provide utmost value to our customers across multiple markets.

Challenges

The key challenge in this project will be bringing together cutting edge technologies from different fields: satellite communications, IoT infrastructure, industrial sensing, public cloud, and combining them together into the R3 IoT service to best meet the needs of our customers and users.

System Architecture

At a top level, the R3 solutions is composed of two main elements: the first is R3Cell, the smart gateway that is deployed in the field and which bridges communications between IIoT end-devices such (as sensors) and the multiple backhaul satellite communications back to the cloud. The second is the R3Cloud, a web-based Mission Control Software that receives sensor and other data from all the gateways out in the field and provides the functionality required to manage and control large numbers of deployed devices anywhere in the world.

Plan

Project Milestone Date

Project Kick-Off and Systems 

Requirement Review (SRR)

May 2020

WP1000 Gate Review: Preliminary Design Review (PDR)

 July 2020

WP2000 Gate Review: Critical Design Review (CDR)

October 2020

WP3000 Gate Review: Test and Readiness Review (TRR)

July 2021 

WP4000 Gate Review: Factory Acceptance Test (FAT)

April 2022

Final Review 

August 2022

Current Status

The Project is now complete. All deliverables and documentation will be submitted to ESA as of the 16th August 2022 and the Final Review will be held in the Krucial (formerly R3 IoT) offices on 30th August 2022. Project objectives have been met and certification testing is due to be completed in time for Final Review.