Mobile ad hoc networks with satellite access for public safety operations

STATUS | Completed
STATUS DATE | 11/04/2016
ACTIVITY CODE |
Mobile ad hoc networks with satellite access for public safety operations

Objectives

The objective of this project is the development of a mobile broadband communication gateway for public safety organizations which connects Mobile Ad hoc Networks (MANETs) with different broadband Wide Area Networks (WANs), such as satellite, cellular or terrestrial networks. Therefore, its core feature is the connection of MANETs to different type of WANs. To implement an efficient and reliable connection the gateway needs to perform an integrated mobility and QoS management as well as security functionality.
The development concerning mobility management focuses on providing continuous connectivity between end user devices at the operation site and their respective remote communication partners, while switching the WAN technology or the network point of attachment of end user devices within the MANET. This way the standard connections and, perhaps even more important, the VPN connections to the control centre will remain always active throughout the duration of a public safety operation.  The proposed QoS and security functionality has to be adapted to the deployed mobility management scheme.

The figure below illustrates the usage of the gateway to be developed to provide WAN connectivity, e.g. via satellite, to mobile end user devices connected to a MANET during a public safety operation.

(The above is a sample picture)

Challenges

Among others the following key issues are addressed in the project:
 
  • The demand of public safety organizations for secure, flexible broadband communication at the operation site as well as between the operation site and the control centre.
  • Providing broadband communication that can be used for any data, video or voice applications using the Internet Protocol.
  • Providing continuous connectivity to mobile end devices at the operation site.
  • Developing a solution that addresses the aspects of mobility, security and traffic prioritization fulfilling as much as possible the user requirements of public safety organizations as well.

Plan

The project has a total duration of 24 months. The work to be performed in this project is mapped into five work packages:
  • Project and Quality Management: Overall project management including project planning, project administration, etc.
  • Collection of user requirements: Collection and specification of end user requirements
  • Performance of system design: Design of initial and final system architecture, considering the end user’s mobility, security and QoS requirements.
  • Performance of software development: Specification of the software architecture for the new functions for mobility, security and QoS management for the MANET with satellite access prototype
  • Test and verification: Verification of the prototype

Current Status

The project started on June 19, 2013. At the beginning of the project the user requirements due to the communication of the target customers have been identified. For the identification of the user requirements IABG interviewed several public safety organizations. The interviews comprised a wide spectrum of interview partners providing an international and comprehensive view of the public safety sector. Due to the output of these interviews a set of requirements have been generated.

Suitable technologies have then been identified for solving the mobility issues in scope of the project. The trade-off between possible technologies to achieve the required functionalities has been outlined.

The gateway prototype system was broken down into subsystems. The subsystems for the mobility, QoS and security solution to be developed have been specified within the final system architecture. The prototype implementing the specified system architecture has been built for the proof of concept.

Finally, the prototype and thus the system architecture have been evaluated in typical user scenarios by performing field tests in cooperation with public safety organizations. The organizations provided the test environment including their specific user devices and their WAN communication solutions.

The project was successfully concluded on December 17, 2015.